India’s First Bullet Train to Start in Late 2027

India’s first bullet train service is expected to begin operations in the final quarter of 2027, with the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail corridor opening first. Railway Minister Ashwini Vaishnaw confirmed the revised timeline on Friday, November 20, outlining construction progress and plans for indigenously manufactured high-speed trains.

Surat-Vapi Section to Open First

The initial service will operate between Surat and Vapi in Gujarat, covering approximately 100 kilometres.

The remaining sections of the 508-kilometre Mumbai-Ahmedabad corridor will become operational in phases as construction progresses.

Vaishnaw said the project had achieved significant progress despite earlier delays caused by land acquisition difficulties and the COVID-19 pandemic.

Construction Progresses on Bullet Train Corridor

According to the Railway Minister, 456 kilometres of pier work and 371 kilometres of viaduct construction had been completed by September 2026.

Around six lakh noise barriers have been installed along 299 kilometres, while 9,300 overhead electrification masts have been erected across 206 kilometres of viaduct.

Four mountain tunnels have also been excavated.

Work continues on a 21-kilometre underground tunnel in Maharashtra, including a seven-kilometre section beneath Thane Creek.

Indigenous Bullet Trains Under Development

Indian manufacturers Integral Coach Factory and BEML are developing B28 high-speed trainsets designed to operate at speeds of up to 280 kilometres per hour.

Track trials are expected to begin around the middle of 2027, ahead of the planned passenger service.

The project also involves Japanese technical cooperation and high-speed railway technology.

Once completed, the corridor is expected to significantly reduce travel time between Mumbai and Ahmedabad.