Maharashtra Halts Adani’s Tarali Hydropower Project
The Maharashtra Forest Department has ordered an immediate halt to work on Adani Green Energy Limited’s 1,500 MW Tarali Pumped Storage Project in Satara district, citing the absence of mandatory wildlife clearance. The November 13 order follows questions over a revised project cost estimate that reduced the calculated wildlife conservation contribution from ₹227 crore to approximately ₹2.27 crore.
Forest Department Flags Missing Wildlife Approval
Forest officials issued show-cause notices after an inspection found construction activities underway without prior approval from the National Board for Wildlife (NBWL).
The department directed the company to stop all work and submit an explanation within three days, along with statutory approvals, site maps and tree-cutting permission documents.
Officials warned that failure to provide satisfactory documentation could result in action under applicable forest and wildlife laws.
Adani Project Cost Revision Raises Questions
The project’s original estimated cost was ₹5,675 crore. However, a September 2026 affidavit cited a revised figure of ₹56.75 crore.
The change reduced the calculated 4% wildlife conservation contribution from ₹227 crore to ₹2.27 crore. The company subsequently deposited ₹56.75 lakh with Sahyadri Tiger Reserve.
The Union Environment Ministry directed an investigation on November 6 following a complaint questioning the revised cost.
Adani Green Denies Violating Environmental Rules
Adani Green rejected suggestions that it deliberately reduced project costs to minimise conservation payments.
The company clarified that ₹56.75 crore represented survey and investigation expenses rather than the total project cost.
It maintained that the project occupies private, non-forest land and had secured environmental clearance in February 2025 and consent to establish in April 2025.
Adani Green also said its wildlife clearance application remained under consideration and that construction began after obtaining the necessary permissions.
The disagreement over regulatory compliance remains unresolved.